400 Tons in the Air

Major Maintenance Underway at the Gönyű Power Plant
Gönyűi Erőmű karbantartás

Major maintenance is being carried out on the gas turbine at the Gönyű Power Plant for the third time. The work, which began in early September, is expected to last until mid-October.

The major maintenance is proceeding according to a specific schedule. After the preparatory disassembly works, the dismantling of the gas turbine began on 4 September. One of the most spectacular and technically complex parts of the project was the removal of the 111-ton gas turbine rotor, which took place in the first half of September.

Following this, reassembly work may begin in the second half of September, with commissioning planned for early October. The complete major maintenance is expected to be finished by mid-October.

During major maintenance, the gas turbine is completely dismantled. Parts and blades that come into contact with hot gas are replaced, and the generator is also inspected and maintained.

This type of major maintenance for gas turbines typically becomes necessary every 4–6 years, depending on operating conditions and the number of operating hours. At the Gönyű power plant, significant maintenance and refurbishment works previously took place in 2017 and 2021.

400-Ton Load Test Performed by the Machine Room Overhead Crane

One special task in the safe preparation for major maintenance was the load test of the engine room’s overhead crane.

The overhead crane located in the Gönyű Power Plant’s engine room has a nominal rated load of 370 tons, and plays a key role during major maintenance, as it is used to move the heavy components of the gas turbine and the generator. Some components to be lifted can weigh up to 320 tons.

Therefore, the crane was tested before major maintenance. The dynamic load test was carried out at 110 percent of the nominal rated load, so the test load for the 370-ton crane was approximately 400 tons.

The purpose of the test was to verify that the crane operates safely under extreme load, that the brake systems work properly, and that overload protection is correctly set.

The approximately 400 tons of test weights arrived from Austria, requiring a total of 21 trucks for transport. The test weights were originally part of the counterweight system of a crane with a 1000-ton rated load.

A 400-ton load test is a special operation: few overhead cranes of this size exist in Hungary. During the test, the crane operator, riggers, and specialists responsible for lifting worked together under strict work area restrictions and continuous communication.

The successful load test confirmed that the crane is properly prepared for the lifting tasks it will face during major maintenance.

About 150 Specialists Working on the Project

Around 150 specialists are involved in the major maintenance, including directly contracted companies and subcontractors. Approximately 25–35 companies are cooperating in the project.

The primary goal of the major maintenance is to preserve the technical condition of the gas turbine, replace necessary parts, and ensure safe, reliable, and long-term operational security.

After the work is completed, the Gönyű Power Plant will once again be fully available to the Hungarian electricity system, continuing to play an important role in supporting security of supply and system balancing.